Here’s a super condensed version of everything going on this week.
State Road 37 Improvement Project:
Pre-construction at SR 37 & 141st Street is causing changes in traffic configuration.
More information and sign up for text updates on the 37Thrives.com website.
Nickel Plate Trail:
Remaining paving work from 96th Street to 106th Street is underway.
More information on the Capital Project Dashboard website.
Projects North of 116th Street:
Daily lane closures on Cumberland Road due to sanitary and water line work.
Phase 2A traffic restrictions at 146th Street & Allisonville Road.
Additional information on the Hamilton County website.
Projects South of 116th Street:
Sanitary sewer project at 106th Street & Allisonville Road.
Prep work for roundabout construction at 106th Street & Hoosier Road.
New concrete median construction at 106th Street & Kincaid Drive.
Lift station mobilization at Fall Creek Road.
Geist Greenway:
Paving work continues.
More information is on the Play Fishers website under Geist Greenway.
Fishers White River Park Survey:
Seeking public input on new park and trail network.
Feedback can be submitted at playfishers.com/WhiteRiverPark and fishers.in.us/Trails until July 31.
Open House event on August 24 for Fishers Greenways & Trails.